| No. | Project Name | Description | Stage |
| Flooring Replacement (2010) [Not shown on map] | Replacement of carpet, VCT and/or vinyl and wall base at Traffic Division, Animal Control, Facilities/Construction Management and the Bursey Road senior Center. In adidtion, flooring replacement for Police Department has also been included in this project. | Planning | |
| HVAC Replacement (2010) [Not shown on map] | Replacement of five roof top units including four units at Fire Administration building and one unit for Municipal Courts' server room. | Planning | |
| Interior/Exterior Renovations (2010) [Not shown on map] | Painting the interiors at Traffic Division, Animal Control, and Facilities/Construction Management. Painting the interior and exterior at the Bursey Road Senior Center. | Planning | |
| NRH Recreation Center [TIF #2] (Not shown on map.) | This project provides for design and construction of a recreation center up to 100,000 square feet and will include indoor leisure and aquatic features. Other indoor amenities may include a double gymnasium, expansive fitness center, indoor walking track, classrooms, pre-school/day care room, banquet/meeting space, kitchen facilities, showers, lockers and administrative offices. | Design | |
| 01 | 820 Widening / City Hall Modifications | Purchase properties adjacent to City Hall for future modification of the facility and parking lots as a result of the widening of Loop 820. | Ongoing |
| 02 | 820 Widening - Professional Services | Due to the anticipated widening of Loop 820 the City needs the assistance of outside professional services to assist in managing the project purchase of several parcels of City owned land. The services will include legal council, archtectural services, property appraisals and others as needed. | Ongoing |
| 03 | Concrete Repairs to Fire Station #2 | The purpose of this project is to remove and replace 1,900 square feet of the 10 ft. wide by 190 ft. long access drive along the open channel, including flumes. The concrete drive is bordered on the north side by a concrete drainage channel, where there is major cracking and sub grade failure. | Construction |
| 04 | Davis Boulevard Property Acquisition - TOD Area | Purchase of 11.809 acres of land at Davis Boulevard north of Main Street. | Ongoing |
| 05 | NRH Animal Adoption & Rescue Center Expansion | This project entails the redesign and renovation of the existing 6,747 sq ft animal shelter with an expansion of roughly 8,000 additional sq ft. The renovated and expanded facility is anticipated to provide a total holding capacity of 162 animals. The existing shelter houses on average 102-120 animals daily with a current design capacity of 95. The project will provide additional kennel capacity, adoption areas, sick and incoming animal isolation areas, and a separate entry and exit to reduce cross-contamination issues, as well as additional storage space and working areas. | Planning |
| 06 | Additional City Hall UPS (2010) | Purchase of an additional UPS for City Hall to provide un-interrupted electrical power to essential operating systems during power outages, prior to the generator coming on-line. | Construction |
| 07 | Community Center - South of Loop 820 | Renovation of the former Food Lion building at 4131 Rufe Snow Drive. The facility will provide library and recreation services and community meeting space. | Planning |
| 08 | Fire Station 2 Generator Upgrade/Replacement | Replacement of the existing generator system at Fire Station 2 and adding receptacles to critical equipment. | Planning |