Drainage Continuing and Proposed Projects





Click here for larger map.

No.Project NameDescriptionStage
 Channel Cleaning / Street Drainage Imp. 2008 (not shown in map above)This is an annual program that consists of cleaning out sediment that has built up significantly throughout the years in some of the City's earthen channels. This project also consists of repairing curb & gutter sections that currently pond water in existing streets.Ongoing
1Iron Horse Golf Course Drainage Imp.This project consists of constructing a 12" and 18" gabion mattress along the south side of Tee Box No. 1 where Singing Hills Creek discharges into Big Fossil Creek. This project will also include the construction of a 12" and 18" gabion mattress along the south bank of Big Fossil Creek where it crosses the fairway at Hole No. 16.Engineering
2Little Bear Creek Drainage ImprovementsThis is a future project.Planning
3Meadowview Estates ChannelThis is a future project. Planning