Bedford Euless Road Improvements

road work ahead

July 21, 2023 Update

Starting Monday, July 24, contractors will be closing Colorado Boulevard and Strummer Drive at Bedford Euless Road for paving operations. Maple Street and Nevada Trail will be open for area residents to access their neighborhood. All businesses along Bedford-Euless Road continue to be accessible. Please slow down and watch for workers in this area. 

May  15, 2023 Update

As of late Friday (May 12) two-way traffic on Bedford Euless Road was reestablished. Work continues on the northern side of the roadway including installation of sidewalks, ADA ramps and paving at the intersections of Maple, Nevada and Eldorado.  Access to Colorado Boulevard and Strummer Drive from Bedford Euless remains open. 

April 24, 2023 Update

Starting today, Bedford Euless Road will be reduced to one-way eastbound traffic only between Boulevard 26 and Strummer Drive. The one-way traffic is expected to last for two to three weeks (dependent upon the weather) while new concrete pavement is being placed on the northern half of the roadway. All westbound traffic is being detoured via Strummer Drive to Boulevard 26. 

April 21, 2023 Update

The switch to one-way traffic on Bedford Euless Road has been rescheduled. We now anticipate it to start early next week. We will provide an update on the timing once we get confirmation.

April 19, 2023 Update

Starting Friday, April 21, Bedford Euless Road will be reduced to one-way eastbound traffic only between Boulevard 26 and Strummer Drive. The one-way traffic is expected to last for two to three weeks (dependent upon the weather) while new concrete pavement is being placed on the northern half of the roadway. All westbound traffic will be detoured via Strummer Drive to Boulevard 26. 

Businesses on Bedford Euless Road will remain open and accessible to eastbound motorists during this phase of construction. We anticipate there being one more period of one-way traffic when the final concrete lanes are poured in early summer. 

Text Bford to 888777 for lane closure and construction updates.

The Bedford Euless Road reconstruction project is part of the city’s 2020 Street Bond Program. You can learn more about street improvements included in the bond program at www.nrhtx.com/2020bond

Detour Map

Bedford Euless One Way Traffic Detour

Printable Detour Flyer

Oct. 19, 2022 Update

Traffic lanes on Bedford Euless Road will be shifting to the southern side of the roadway between Booth Calloway Road and Strummer Drive, so that the contractor can begin working on the northern side of the street. The eastbound lane is expected to shift on Thursday, followed by the westbound lane on Friday. Please slow down, watch for workers and pay extra attention when traveling in this area. The speed limit in the construction zone is reduced to 30 mph. 

Access to restaurants and other businesses on Bedford Euless will remain open throughout construction. Access to Colorado Boulevard and Strummer Drive from Bedford Euless will also remain open. Access to Maple Street, Nevada Trail, and Eldorado Drive from Bedford Euless will be closed during this phase of construction. Detour routes will be placed throughout the neighborhood. Improvements to Bedford Euless Road are part of the 2020 Street Bond Program. Learn more at www.nrhtx.com/2020bond

Sept. 23, 2022 Post

If you’re wondering about the big hole that’s been dug on Bedford Euless Road in front of Ernie’s Seafood, it’s for improvements to the underground storm drain system. This work will take approximately 1 month, weather permitting. Once that’s finished, they’ll get started on reconstructing Bedford Euless Road from Booth Calloway Road to just east of Strummer Drive. Traffic will be reduced to one lane in each direction during the project. Access to restaurants and other businesses on Bedford Euless will remain open. Please slow down and use caution when traveling in this area. 

The improvements to Bedford Euless Road are part of the 2020 Street Bond Program. You can learn more about the street bond projects at www.nrhtx.com/2020bond.

Bedford Euless construction

Facebook Twitter Email

Other News in City News

construction vehicles performing roadway subgrade work

Word on the Streets

Posted on: September 28, 2023
containers of oil, gas, cleaning chemicals and paints

Household Hazardous Waste

Posted on: September 27, 2023
Fire Station Open House - October 9-13 from 6pm-8pm

NRHFD Open House

Posted on: September 25, 2023
two young swimmers in water, Pool Safely logo

Grant Award

Posted on: September 19, 2023
Council Chambers.jpg

City Budget & Tax Rate Adopted

Posted on: September 12, 2023
Roadway construction equipment on Iron Horse Blvd

Iron Horse Boulevard Improvements

Posted on: September 8, 2023
water shooting out of ground, with construction equipment in background

Water Main Breaks

Posted on: August 19, 2023
Roadway Asset Services van on street

Citywide Street Assessment

Posted on: August 18, 2023
Nitro Blast

NRH2O New Attraction

Posted on: August 16, 2023
Lane Closed Sign

Glenview Drive Improvements

Posted on: August 14, 2023
seal (web).jpg

FAQs: Backyard Chickens

Posted on: July 26, 2023
Mike Young standing outside City Hall

New Police Chief

Posted on: July 11, 2023
Set of keys laying on pavement

Lost & Found

Posted on: July 6, 2023
Peppa Pig costumed character waving

Peppa Pig Theme Park

Posted on: June 28, 2023
weather station equipment and speaker on light pole at park baseball field

Park Weather Safety

Posted on: June 23, 2023
Large pavilion with picnic tables underneath, surrounded by trees

Park Pavilion

Posted on: June 16, 2023
K9 Luca wearing vest

K-9 Program

Posted on: May 22, 2023
Dispatcher Chelsea Duncan presented certificate of recognition

Special Recognition

Posted on: May 18, 2023
seal (web).jpg

Oaths of Office

Posted on: May 18, 2023
seal (web).jpg

Compliance Court

Posted on: May 11, 2023
Fire Employees recognized

Special Recognition

Posted on: May 11, 2023
shovels

Groundbreaking

Posted on: May 5, 2023
Street Maintenance - slurry seal being placed on asphalt street

Preventive Street Maintenance Program

Posted on: April 25, 2023
Home

Property Value Notices

Posted on: April 19, 2023
70th Anniversary Seal

NRH Celebrates 70th Anniversary

Posted on: March 31, 2023
seal (web).jpg

Annual Comprehensive Financial Report

Posted on: March 21, 2023
water meter and app

New Water Meters

Posted on: February 28, 2023
seal (web).jpg

Charter Review Task Force

Posted on: January 10, 2023
Street icon

2020 Bond Program

Posted on: November 4, 2020
City Point Rendering

City Point Development

Posted on: December 18, 2019